As an important equipment in industrial production, the safety and reliability of bridge cranes are directly related to production efficiency and personnel safety. Therefore, it is particularly important to formulate a set of comprehensive and strict acceptance standards. The acceptance of bridge cranes is not only a comprehensive consideration of equipment quality, but also a strong guarantee for production safety. From appearance inspection to functional verification, to performance testing and document review, each link is indispensable. The appearance inspection focuses on the integrity, deformation, coating corrosion and clarity of the components to ensure that the appearance of the equipment is flawless and the information is accurate. The functional inspection covers basic functions such as lifting, walking, and luffing, as well as the compliance of safety protection devices and electrical systems to ensure smooth, safe and reliable operation of the equipment. The performance inspection compares the rated lifting weight with the actual lifting weight, examines the performance of the equipment under different working environment conditions, and conducts performance tests in extreme environments to comprehensively evaluate the adaptability and durability of the equipment. In addition, the completeness of the documents is also a key link in the acceptance. The integrity of technical documents, certificates of conformity and maintenance and repair records provides an important basis for the subsequent use and maintenance of the equipment.
Appearance inspection is the initial link in the acceptance of bridge cranes and an important step to ensure the safe and efficient operation of cranes. Through careful observation and inspection of the crane as a whole and its components, it can be preliminarily determined whether there are obvious defects, damage or safety hazards. This link not only helps to discover and solve potential problems in a timely manner, but also provides an important reference for subsequent acceptance work.
In the appearance inspection of bridge cranes, the integrity and deformation of components are one of the key points of attention of acceptance personnel. They need to check each component of the crane one by one, including key components such as the main beam, end beam, trolley frame, drive device, brake, etc., to ensure that there is no missing or damage. For the problems found, the acceptance personnel need to record and report them in time for subsequent repair or replacement. At the same time, it is also necessary to observe whether these components have deformation phenomena, such as deflection of the main beam and distortion of the end beam. These deformations may affect the stability and carrying capacity of the crane, causing problems such as jitter and increased noise during the operation of the equipment, and even cause safety accidents.
Surface coating and corrosion are key links in appearance inspection. The surface coating not only plays a role in aesthetics, but more importantly, it can protect the crane from corrosion. During acceptance, it is necessary to check whether the coating is uniform, without peeling or cracking, and whether there is corrosion such as rust and oxidation. Any problems found should be repaired or replaced in time to extend the service life of the crane.
Bridge cranes are usually equipped with various signs and labels, such as rated lifting weight signs, safety warning signs, operating instructions, etc. These signs and labels are of great significance for guiding operations and reminding safety. During acceptance, it is necessary to check whether these signs and labels are clear, accurate, and unobstructed to ensure that operators can obtain the required information at a glance. In addition, it is necessary to check the fixing of the signs and labels to ensure that they are not easy to fall off or accidentally damaged.
Overhead Crane Identification and Signage Checklist
Serial number | Signage type | Inspection content | Inspection results (Yes/No/Remarks) |
1 | Rated lifting capacity marking | Whether the marking is clear and accurate, without blockage or blurring | _ |
2 | Safety Warning Signs | Whether the logo is complete, the content is accurate, and it is easy to identify | _ |
3 | Operation guide or instructions for use logo | Is there a detailed operation guide, and is the content accurate and easy to understand? | _ |
4 | Manufacturer and production date identification | Whether the logo is clear, the manufacturer’s information is complete, and the date is accurate | _ |
5 | Maintenance logo or guide | Is there a maintenance guide, is the content detailed and easy to operate? | _ |
6 | Certificate of conformity or inspection report identification | Is there a certificate of qualification or the latest inspection report mark? | _ |
7 | Fixing of signage | Whether the signage is firmly installed, not easy to fall off or be accidentally damaged | _ |
8 | Additional safety or operating instructions signs | Is there any additional safety tips or operational precautions identification | _ |
Detailed inspection list for bridge crane appearance
Type of inspection | Inspection details | Inspection results (pass/fail/remarks) |
Component integrity check | No loss or damage to the main beam | _ |
No loss or damage to the end beam | _ | |
The trolley frame is intact and has no damage | _ | |
The drive device is not missing or damaged. | _ | |
The brake is not missing or damaged. | _ | |
Component deformation inspection | No deflection of main beam | _ |
No distortion of end beam | _ | |
No deformation of the trolley frame | _ | |
Surface coating inspection | Uniform coating, no peeling or cracking | _ |
Corrosion inspection | No rust, oxidation or other corrosion phenomena | _ |
Other appearance inspection | The connectors are tight and not loose, and the welds are free of cracks. | _ |
The overall structure is stable, without obvious shaking or abnormal noise | _ |
Functional inspection is a key step to verify whether the functions of the bridge crane are normal, and it is also an important guarantee to ensure the normal operation of the equipment and safe production. By simulating actual operation, you can intuitively understand the performance of the crane, timely discover and solve potential problems, and ensure that the crane can stably and reliably complete various tasks during normal use.
Lifting, walking, and luffing are the three basic functions of bridge cranes, and they are also one of the most frequently used functions in daily life. In order to ensure the normal operation of these functions, these functions need to be tested in detail during acceptance. First, for the lifting function, it is necessary to test the stability and accuracy of the lifting mechanism to ensure that the lifting mechanism can lift and lower the goods smoothly and accurately. During the test, the performance of the crane can be observed by simulating the lifting operation in actual work to ensure that it can meet the work requirements. Secondly, for the walking function, it is necessary to test the stability and stability of the walking mechanism to ensure that the walking mechanism can move smoothly along the track. During the test, the mobile performance of the crane can be observed by simulating the walking operation in actual work to ensure that it can meet the work requirements. Finally, for the luffing function, it is necessary to test the flexibility and accuracy of the luffing mechanism to ensure that the luffing mechanism can adjust the amplitude of the goods as required. During the test, the amplitude adjustment performance of the crane can be observed by simulating the amplitude change operation in actual work to ensure that it can meet the working requirements. In addition to the above test contents, it is also necessary to pay attention to whether there are abnormal sounds, vibrations or jamming phenomena. These phenomena may be manifestations of problems with the equipment and need to be discovered and resolved in time.
The safety protection device is an important part of the bridge crane. Its function is to prevent the crane from being dangerous under abnormal conditions. In order to ensure the safe operation of the equipment, it is necessary to check whether various safety protection devices are intact and effective during acceptance. First, it is necessary to check whether the limit switch is sensitive and reliable and can accurately limit the range of motion of the crane. Secondly, it is necessary to check whether the overload protection device can effectively prevent the crane from overloading, thereby avoiding equipment damage or safety accidents. It is also necessary to check whether the buffer can effectively absorb the impact force of the crane during movement, thereby protecting the equipment from damage. The integrity and effectiveness of these safety protection devices are directly related to the safe operation of the equipment and the life safety of personnel. Therefore, during the acceptance process, it is necessary to strictly check whether these devices are working properly, whether there is damage or failure. If any problems are found, they need to be repaired or replaced in time to ensure that the safety performance of the equipment meets the requirements.
The electrical system is the power source and control center of the bridge crane. In order to ensure the normal operation of the equipment and the safety of personnel, the electrical system needs to be inspected during acceptance. First of all, it is necessary to check whether the electrical system complies with relevant national standards and regulations. This includes aspects such as cable laying, wiring terminals, and electrical components. The laying of cables should be neat and standardized, the wiring terminals should be firm and reliable, and the electrical components should meet the requirements of the specifications. Secondly, electrical performance testing is required. This includes testing the insulation resistance and grounding resistance of the electrical system to ensure that the electrical system can work stably and reliably. It is also necessary to test the logic and reliability of the control system to ensure that the control system can work normally and ensure that the safety performance of the equipment meets the requirements.
Performance inspection is the core link in the acceptance and operation and maintenance process of bridge cranes. It aims to comprehensively evaluate and verify whether the actual operating performance of the crane under various working conditions meets or exceeds the design standards and expected requirements. By conducting meticulous and rigorous performance tests on each key system and component of the bridge crane and comparing and analyzing it with its rated standards, it is possible to accurately determine whether the important performance parameters such as the load-bearing capacity, stability, safety and service life of the crane when performing lifting operations meet the standards.
As the most basic and core performance indicator of bridge cranes, the rated lifting capacity not only represents the upper limit of the crane’s lifting capacity, but also is a key factor in ensuring the safe and stable operation of the entire system. This indicator is directly related to many technical details such as the main structural dimensions, power configuration, hydraulic system efficiency and design load of the hook pulley block of the crane. During the acceptance stage, the actual lifting capacity must be accurately measured in strict accordance with national standards and industry specifications through rigorous scientific experimental methods to ensure that the actual test results are consistent with the rated lifting capacity provided by the manufacturer, so as to ensure that there will be no structural damage, mechanical failure or electrical control system failure due to overload during use.
The working environment of the bridge crane has an important impact on its performance. During acceptance, it is necessary to check whether the working environment of the crane meets its design requirements and use conditions, including temperature, humidity, dust concentration and other aspects. In a high temperature environment, the hydraulic system, motor and other components of the crane may be affected, resulting in performance degradation. In a low temperature environment, the lubricating oil may solidify, affecting the lubrication effect and causing accelerated wear of the equipment. In an environment with high dust concentration, the equipment may be corroded and worn. Therefore, it must be taken seriously.
In order to fully verify the reliability and stability of the bridge crane under various complex working conditions, a series of performance tests under extreme conditions need to be carried out during the acceptance process. For example, under extremely high temperature conditions, the cooling system, lubrication system and electrical control system of the crane are comprehensively inspected to ensure that it can still maintain a stable operating state under high temperature environment and effectively prevent safety hazards caused by overheating of the equipment; in an extremely low temperature environment, attention should be paid to the performance of the hydraulic oil, grease and other oil products of the crane, as well as the starting performance and flexibility of each component, to prevent problems such as stiffness, freezing or difficulty in starting the equipment due to low temperature.
Special tests are essential for the influence of strong wind and vibration environment. Under strong wind conditions, it is necessary to verify whether the crane’s wind resistance meets the standards, including but not limited to stability assessment under tailwind, headwind and crosswind conditions; in a vibrating environment, it is necessary to evaluate the crane’s seismic performance during the hoisting operation, such as fatigue analysis of structural parts, and inspection of key components for looseness or damage, so as to ensure that the crane can maintain a good operating state and sufficient load-bearing capacity when facing harsh working conditions.
The document completeness inspection is a key link in the acceptance process of bridge cranes, and its importance cannot be ignored. This inspection is intended to ensure that the design, manufacture, installation and use of bridge cranes strictly comply with national and industry requirements and standards. By carefully checking the relevant technical documents, certificates of conformity, maintenance records and repair records and other detailed information, the compliance and safety of the crane can be fully verified, providing strong guarantees for subsequent normal operation and maintenance.
The technical documents cover the entire process of bridge cranes from design to installation, including but not limited to design drawings, process documents, inspection reports, etc. These documents are not only the guiding basis for the manufacturing and installation process, but also reflect the performance characteristics and safety standards of the crane. During acceptance, it is necessary to check whether these documents are complete, accurate and compliant. At the same time, it is also necessary to check whether the crane’s certificate of qualification is valid to ensure that the crane has passed the inspection and certification of the relevant departments.
Maintenance records and repair records are important bases for reflecting the use and maintenance of bridge cranes. These records include daily maintenance records, regular maintenance records, and repair records. During acceptance, it is necessary to check whether these records are complete, detailed, and traceable. These records help to understand the historical status of the crane and provide important references for subsequent maintenance and maintenance. At the same time, it is also helpful to discover possible problems and hidden dangers in the use of the crane, and take timely measures to repair and improve it.