Homeالأخبار → Crane loading and inspection procedures

Crane loading and inspection procedures

Cranes over 3 tons are special equipment, so cranes over 3 tons need to be inspected , including bridge cranes for indoor use and gantry cranes for outdoor use. Some business friends who have installed crane equipment do not know much about the installation notification and inspection procedures. I will give you a brief introduction here.

Reporting unit

The following is the inspection procedures for regular inspection and installation and modification of special equipment, which should be handled by the local special equipment inspection and testing department.

A. The installation, transformation, and maintenance construction unit notified by the special equipment safety supervision and management department.

1. Inspection procedures

(1) Inspection application

The construction unit submits the following materials to the center business hall to apply for inspection:

1. The "Special Equipment Installation, Modification and Maintenance Notice" accepted and filed by the special equipment safety supervision and management department and relevant materials provided at the time of notification.

2. Special equipment installation, transformation, maintenance construction technology, plan and construction drawings;

3. Self-inspection records or completion data of installation, modification and maintenance;

4 "Application for Supervision and Inspection of Special Equipment Installation, Modification and Maintenance".

(2) Acceptance

1. Special personnel in the business hall will accept.

2. The acceptor confirms the applicant's or personal information, reviews the legality, authenticity, and comprehensiveness of the content of the materials submitted by the applicant in accordance with the requirements of the special equipment safety technical regulations, and informs the applicant that the entire content of the materials needs to be supplemented and corrected at one time.

3. According to the actual construction progress, the applicant and the accepting staff shall agree on the staged supervisory inspection items and dates.

4. The accepting staff informs the applicant of the inspection cooperation matters in writing, and issues a notice of acceptance of inspection application.

(3) Communication

1. The accepting personnel should promptly assign supervisory inspection tasks, and the inspectors who accept the task should contact the construction unit before the agreed inspection date to confirm the on-site preparations.

2. The construction unit shall, before the agreed inspection date, prepare for on-site inspection in accordance with the inspection work cooperation requirements notified in writing by the accepting personnel, and promptly ask the accepting personnel or inspectors for unclear matters. If there is a change in the construction progress, it should be communicated with the acceptor or inspector in time to re-negotiate the inspection date.

Four, supervision and inspection

1. Inspectors who hold relevant inspection qualification certificates shall carry out supervision and inspection in accordance with safety technical specifications and standards for special equipment.

2. If the content of the reported materials is inconsistent with the on-site situation, the right to refuse the supervision and inspection, and issue the "Supervisory Inspection Work Contact Form" on site to inform the construction unit or manufacturing unit; if the situation is serious, issue the "Supervisory Opinion Notice", and Report to the special equipment safety supervision and management department immediately.

3. After the inspection work is completed, the inspector should inform the construction unit or the user of the equipment safety status and rectification time limit in writing, and should immediately report to the special equipment safety supervision and management department if serious accidents are found.

4. After the inspection work is completed, the inspector shall issue a notice of charges in accordance with the inspection items and the document No. 170 of Hunan Price Fee [2006], and shall inform the applicant of the time limit for handling the relevant procedures.

(5) Issuing the report

1. On-site inspectors should issue supervisory inspection reports and supervisory inspection acceptance in an objective, fair and timely manner. The inspection and approval personnel of the inspection and testing agency are responsible for signing the supervision and inspection conclusions.

2. General equipment supervision and inspection shall be issued within 10 working days, and large equipment shall be issued with a supervision inspection report and a supervision inspection certificate within 30 working days.

B. Application, acceptance, inspection, and report issuance of regular inspection and transfer appraisal of special equipment in use.

2. Declaration

(1) Declarant:

Units or individuals that use registered special equipment in the special equipment safety supervision and administration department.

(2) Time limit for declaration:

1. 1 month before the expiration of the validity period of the special equipment safety inspection.

2. Before reactivating the equipment that has been inactive for more than 6 months.

3. Before the equipment required for transfer appraisal is ready for transfer.

(3) Application procedures:

1. Inspection

1.1 Equipment users or individuals can apply for inspection at the center business hall or online.

1.2 If the equipment transfer appraisal is required, bring the following materials to the center business hall for inspection:

◎Certificate of the unit accepting the equipment;

◎Special equipment registration certificate;

◎Equipment technical files.

1.3 Fill in the inspection application

2. Acceptance

2.1 The staff in the business hall are responsible for accepting online inspections and hall inspections.

2.2 The accepting personnel carefully check the correctness of the applicant's or personal information and the submitted materials, and should ask the applicant to supplement if the information is incomplete.

2.3 After confirming that all the materials submitted by the applicant are correct, the inspection date shall be agreed with the applicant and the acceptance notice (only for inspection in the center business hall) shall be issued, and a written statement of the rejection shall explain the reasons for the rejection.

2.4 Regular inspection of general equipment, 10 working days before the validity period of the license, and regular inspection of large equipment 30 working days before the validity period.

2.5 The accepting staff shall inform the applicant in writing of the cooperation matters of the inspection work.

3. Communication

1. The accepting personnel shall issue inspection tasks in time, and the inspectors who accept the tasks shall get in touch with the construction unit before the agreed inspection date to confirm on-site preparations.

2. The reporting unit shall prepare for on-site inspection in accordance with the inspection work cooperation requirements notified in writing by the accepting personnel before the agreed inspection date, and promptly ask the accepting personnel or inspectors for unclear matters. If you need to reschedule due to special reasons, you should communicate with the accepting personnel or inspectors in a timely manner to re-arrange the inspection date, but it shall not exceed the validity period.

3.  Inspection

1. Inspectors holding relevant inspection qualification certificates shall conduct regular inspections on special equipment in use in accordance with special equipment safety technical specifications and standards.

2. After the inspection work is completed, the inspector shall inform the applicant in writing of the safety status of the equipment and the time limit for rectification, and shall immediately report to the special equipment safety supervision and management department if any serious accidents are found.

The inspection requirements for special equipment cranes may vary from place to place, and everyone should follow the requirements of the local department.

  الاتصال لدينا كرين المتخصصين


أرسل لنا رسالة وسوف نقوم بالرد عليك في أقرب وقت ممكن.

    ارسال الاحتياجات الخاصة بك

      arArabic