Many workshops built in the early years used concrete structures, and their crane beams were also concrete. After the secondary grouting layer of the رافعة السكك الحديدية شعاع foundation of some factories was damaged or the embedded bolts broke, the concrete crane rail beam and the steel rail could not be fixed, and the track shifted and fractured. universal. The problem of track fixing of concrete crane rail beams can be solved by installing steel structure fasteners. Editor Yu Zheng found some information on the Internet and shared it with everyone
At present, the construction of factory buildings adopts the method of steel structure welding construction. Steel structure construction has the advantages of short construction period and fast project progress. However, the production plants of some enterprises are still the 20th century brick-concrete structure factory buildings. The main load-bearing component of the lifting equipment is a concrete-cast reinforced concrete crane rail beam. The crane rail beam is prefabricated in advance. The رافعة المسار is positioned by bolt connection. As the service life increases, the embedded bolts of the concrete crane rail beam are more likely to break. Generally, bridge cranes (double beam cranes) have poor track fastening and positioning. Therefore, it is necessary to take certain measures to achieve track positioning and fixation without replacing the concrete crane rail beams.
In the way of fixing the track on the concrete crane rail beam, the standard design form is generally adopted
The fixed connection between the crane rail beam and the track above the track is in the form of bolt connection (see Figure 1). The track pad is laid on the upper end of the track and the beam to adjust the error during the installation of the crane rail beam. The lifting equipment runs above the track for a long time. Vibration, rail gnawing and other reasons cause the connecting bolt to break and the track displacement, which cannot guarantee the track installation accuracy at the initial stage of installation.
The main difference between the two forms of concrete crane rail beam and track connection and fixation (see Figure 2) is that the bolts are set in different ways: one is to reserve bolt holes (bent holes) when concrete is poured, and the existing bent bolts are inserted during installation. Insert the bend hole and fix it; the other is the pre-embedded connecting bolt, which is fixed when the track is installed. After the on-site track connecting bolts are broken, the bent bolts are difficult to remove and penetrate, and the pre-embedded bolts cannot be processed on-site. The crane rail beam needs to be replaced if it is thoroughly processed.
To try to realize the effective positioning and fixing of the track without replacing the crane rail beam, firstly, the structural size of the crane rail beam was measured, and the analysis concluded that the track can be fixed by local steel structure fixing.
After the rail bolt is broken, the rail mainly undergoes lateral displacement. In order to achieve accurate positioning of the rail, steel structure fasteners can be designed and manufactured, and the two-way lateral displacement of the rail can be controlled by the reinforced side plate on the side of the rail beam.
The steel structure fasteners were installed on the upper part of the driving crane rail beam in the main span area of the 40t converter production line of the first steelmaking plant of Bayi Iron and Steel Co., Ltd. The fasteners were installed by the steel structure to realize the positioning and installation of the track and eliminate The hidden dangers of track displacement and fracture.
Schematic diagram of steel structure integral fastener production and installation
Figure 4 Schematic diagram of production and installation of integral fasteners of steel structure
The reconstruction of the concrete crane beam is only a suggestion. If the plant is seriously damaged, the best way is to demolish and rebuild.