Single-beam cranes, double-beam grab bridge cranes , double-beam hook bridge cranes, and explosion-proof bridge cranes are widely used in industrial and mining enterprises. In order to reduce the problems in the later use process. After purchasing a good bridge crane, the enterprise must pay attention to the installation to ensure the quality of the installation. The editor will share with you some points that need to be paid attention to when installing bridge cranes indoors:
For a factory building, the bridge crane can be installed prior to the installation of other equipment, so that it can be fully utilized for frequent transportation and hoisting during the installation of other equipment. Companies need to do the following:
1) Obtain the cooperation of the civil construction unit, and prepare the crane beam in advance for the installation of the track;
2) Obtain the cooperation of construction and supervision units and equipment suppliers to deliver the complete set of bridge crane equipment in advance. This also requires the company to make advance reservations to avoid affecting the overall progress due to the production cycle;
3) Organize the strength, select the correct construction method, and hoist the bridge crane in place on the track as soon as possible;
4) Clean, refuel and energize the bridge crane in the shortest time. If necessary, a temporary power supply can be installed for use.
El grúa de la pista installation is generally performed by the factory construction party cooperating with the enterprise. In order to avoid problems when installing the crane, it must be installed and tested in accordance with the track installation requirements.
Generally, the bridge crane can be assembled on the ground and then hoisted onto the track by a crane as a whole. The hoisting point should be determined according to the structure of the bridge crane, the weight and the center position of the bridge body, trolley and cab.
During the overall hoisting, in order not to affect the equipment on the trolley, the trolley is generally fixed on the outside of the wire rope and close to the binding point.
1) In order to avoid the second displacement of the bridge body in the workshop, the two halves of the bridge body should enter the workshop in order and orientation, unloaded at the designated location and assembled. To do this, the position and the bridge crane cab should also be considered. Direction of hoisting rotation.
2) The bridge body that enters the factory building must be assembled with bolts after being solidified and leveled to ensure that the wheels of the bridge crane are on the same plane.
3) The special connecting plates of the two halves of the bridge body must be assembled according to the manufacturer's mark. To tighten the connecting bolts, both cross-tightening and split-tightening methods should be used at the same time, not one-time tightening.
In individual industrial plants, there are bridge cranes with a width greater than the column spacing of the plant. Whether this type of bridge crane can be hoisted as a whole must be determined through calculations.
Some old factory buildings have been modified to install cranes, but the headroom height of the factory buildings is not enough, and the overall hoisting may not be possible. If the cooperation of the civil construction unit is needed, partial roof slabs can be reserved so that the boom can be extended out of the roof for overall hoisting.
The familiar saying is "three-point quality, seven-point installation". Only with good quality cranes and qualified installation quality can they play their due role in the best possible way.
In order to reduce customer concerns, our factory will have professional installers come to the factory for installation to ensure the quality of the installation, and assist the company in applying for inspection, so that the company's crane can be put into use smoothly.